8. Power connection
10. Starting the machine
- Starting the machine
- 11.
- Shut down/switching off the machine
12. Shrinking operation
8. INSTALLATION
- 2. Before starting the machine please ensure that,
9. POWER CONNECTION
- Blue to Phase3, Black to Neutral and Gray/Green to Earth. Then switch on the MCB.
10. CONTROL PANEL
- Heater MCB
- Controller MCB
- Conveyor ON/OFF
- Conveyor speed knob
- Fan 1 ON/OFF
- Fan 2 ON/OFF
- Heater ON/OFF
- Cooling fan ON/OFF
11. STARTING THE MACHINE
- Connect the machine to appropriate power supply (3 phase). Turn on the Controller MCB to start the machine.
- The Controller MCB is located at the right side of the machine. Then switch ON heater MCB, Heater switch, Fan1 ,
- Fan 2 and Conveyor. The direction of blower as to be verified that it is to be in anti-clockwise direction. The conveyor speed is adjusted by rotating knob present on panel board. To set the temperature, firstly press SET key, then press UP or DOWN key, and at last press SET k...
13. SHRINKING OPERATION
- Special plastic films which shrink on application of heat are used for shrink wrapping. The temperature required for shrinking each film varies and this information can be obtained from the film manufactures.
- Shrink films commonly available are,
- Insert the article in a preformed sleeve or tube of shrinkable film of suitable size. Seal the open ends & make a few holes on the film by pricking it with a pin. The corners of the film may also be sealed cut off for better appearance. If open ends are desired, the ends of th...
- Place the wrapped article on the conveyor at the inlet. The article will come out of the outlet properly shrunk. Inspect the article.