8. INSTALLATION
- Please install the machine according to the following steps: .
- The work table should be horizontal in both the directions. If not, adjust the foot screws to achieve this.
- Check the insulation resistance of the machine between the three phase lines shorted and
- Earth the machine properly and connect the power line ensuring proper phase. This can be
- verified by slightly lifting the film tension pendulum when the film feed roller will rotate in anti clock wise direction when viewed from the left side of the machine. If the rotation is opposite, interchange any two phase lines.
- Install the product push air-cylinder and connect the pneumatic connections to it. Fix its
- Fill the lubricator with oil and give the compressed air connection to the FRL unit. The
- Remove all ties provided for arresting the movement of loose parts. Remove all stretch
12. OPERATION
- Switch on the electric supply and compressed air supply. The pressure gauge on the FRL unit
- shall indicate 6 kg/ sq.cm. If not, adjust the FRL unit. The power on indication lamp will light up. The sealing cylinder, the product push cylinder and the product hold cylinder will come to the home position. (retracted position)
- Load film rolls and lock the film guides. For the convenience of centrally locating the film
- Set the sealing temperature and sealing time.
- Turn the auto manual selector switch to manual mode. Press the seal push button. Now the
- sealing/cutting cylinder will operate. Now both the rolls are sealed into one continuous film.
- Verify the sealing/cutting. If it is not satisfactory adjust the sealing temperature and sealing
- time.Depending upon the size of the packet to be sleeve wrapped, adjust the position of the job stopper guide on the left and the job pusher pneumatic cylinder.