← Back
User Manuals
User Manual for ST_STVLV6
Updated 11 Oct 2026
Applies to: STSTVLV6
9. Power connection
11. Starting the machine
- Starting the machine
- 12.
- Shut down/Switching off the machine
13. Shrinking operation
8. INSTALLATION
- Ensure that the leg assembly is placed on level ground.
- Install the motor-side chain and assemble the chain lock.
- You can adjust the leveling screws to level the machine and slightly adjust its height.
- Before starting the machine, please ensure that:
9.POWER CONNECTION
- 1. Connect the Red wire to Phase 1.
- 2. Connect the Yellow wire to Phase 2.
- 3. Connect the Blue wire to Phase 3.
- 4. Connect the Black wire to Neutral.
- 5. Connect the Gray/Green wire to Earth.
- After making these connections, switch on the MCB (Miniature Circuit Breaker). If all the phase sequences are correct, the phase error LED will not light up. However, if it does light up, it indicates that the phase sequence is incorrect.If the phase sequence is incorrect, you...
10. CONTROL PANEL
- Blower on/off switch
- Heater on/off switch
11. STARTING THE MACHINE
- 1. Connect the machine to the appropriate power supply and switch on the MCB (Miniature Circuit Breaker). You
- 2. Next, switch ON the heater by using the designated heater switch.
- 3. To adjust the conveyor speed, use the knob located on the panel board. Turn it as needed to set the desired
- 4. You can set the required temperature on the temperature controller by simultaneously pressing the "set" and
- the "up/down" buttons. Adjust the temperature to your desired level.
- 5. Once the set temperature is reached, you will notice that the red indication LED on the temperature controller
- turns off. This indicates that the machine has reached the desired temperature and is now ready for use.
- By following these steps, you can safely and effectively start and operate the machine for your intended purpose..
13. SHRINKING OPERATION
- Shrink wrapping using special plastic films that shrink when heat is applied is a common packaging process.
- The temperature required for shrinking each type of film can vary, and this information can typically be obtained from the film manufacturers. Some commonly used shrink films include:
- Here are the steps to perform shrink wrapping:
- 1. Insert the article into a preformed sleeve or tube of shrinkable film that is of a suitable size for the item
- 2. Seal the open ends of the film to encase the article securely. Additionally, it's a good practice to make a few
- holes in the film by pricking it with a pin. This helps prevent air from getting trapped inside the film during the shrinking process. You can also seal and cut off the corners of the film for a neater appearance. If open ends are desired, you can skip the step of sealing the...
- 4. Place the wrapped article on the conveyor at the inlet of the heat tunnel or shrink tunnel. As the article
- moves through the tunnel, the heat will cause the film to shrink and conform tightly around the product.
Documents